CROWLEES PRIMARY SCHOOL HUDDERSFIELD

Project: CROWLEES PRIMARY SCHOOL – HUDDERSFIELD

Value: £80k

Programme Duration: 3 weeks


Scope:
This project was split over two summer holidays with the full replacement of none asbestos ceilings and electrical re-wire throughout a single storey primary school. Asbestos Insulating board debris found extensively above the none asbestos ceilings.

Phased works had to be completed within a tight period to allow for the electrical works to be completed in time for the school re-opening. We supplied multiple teams to site working during the day and on night shifts to ensure continuous presence on site to complete the project within the desired timescale.

The project on both phases was completed on time and with no disruption to the program.