Case Studies

Education

Hopton Primary School

Mirfield

Date Completed: Sept 2019

Project Duration: 2 weeks

We were asked to undertake an innovated asbestos package within the boiler room of a primary school. As with so many school boiler rooms, historic asbestos was found to the walls. In order to stop incurring asbestos costs every few years the school asked for a different approach to the standard removal works. We were asked to install fire proofing panelling to the main walls of the boiler room and then to install brackets to allow for future renovation of the boiler room so that future contractors are not disturbing the asbestos debris to the walls

The works were organised around school holidays to minimise the disruption to the school.

Samuel Alexander Building

Manchester University

Date Completed: Sept 2019

Project Duration: 7 days

We were asked by Manchester University to undertake licensed asbestos works within one of the universities properties during the summer holiday shut down. Works consisted of decontamination under fully controlled conditions within a ceiling void of a classroom and within a service trench.

Tameside College

Ashton under Lyne

Date Completed: Aug 2019

Project Duration: 2 weeks

Unexpected extensive asbestos found throughout the main boiler house of the college after our survey required removal works and encapsulation of the walls. We were instructed following the survey to undertake the works with the minimal effect to the proposed works during the summer holidays.

We were able to allocate considerable resources to the project ensuring weekend working to complete the project as quick as we could for the college in anticipation of the main works.