Case Studies

Leisure

Moon Under Water

Wolverhampton

Date Completed: Apr 2019

Project Duration: 8 weeks

We were asked to undertake the safe removal of extensive asbestos found within the public house section of building no longer in use and vacant by a leading public house chain. The works facilitated extensive asbestos insulating board to the top floor and multiple enclosures on other floors whilst the property on the other side of the door was live and in full operation

Our teams worked 7 days a week in order to complete the project as quickly as possible. We acted as principal contractor for the work and as such provided a temporary welfare and service package as part of our contract.

The forum Theatre

Stockport

Date Completed: Jan 2018 & Apr 2018

Project Duration: 3 weeks in total

We were asked to complete an asbestos removal package to the existing forum theatre over 2 phased visits

Both visits were undertaken at times where the theatre was to undergo refurbishment however adjacent areas of the building were still live and occupied. Due to performance dates happening so close to the works a tight deadline was imposed on the project as a consequence we allocated sufficient resources including weekend working to complete both phases ahead of the agreed timescales.

Great Sankey Leisure Centre

Warrington

Date Completed: Oct 2017

Project Duration: 8 weeks

As part of the wider regeneration of the site, we were asked to put together a package of asbestos removal within the sub floor voids around the main swimming pool. Asbestos had been installed as fire protection to the ceiling of the duct. In order to complete removal we had to break out the duct around the pool in order to free the asbestos material.

Our removal teams constructed purpose built enclosures are around the pool side and undertake mass excavation of the concrete flooring under fully controlled conditions.

Our works were completed on time with no disruption to the refurbishment works being undertaken.